page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124 page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
122 CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
Photo 8.2 Powerhouse and tailrace of the Salleri Chialsa
mini-hydro scheme
8.2 Location of powerhouse
The location of the powerhouse is governed by the penstock
alignment since this building must be located at the end of
the penstock. Apart from this, the following criteria are recom-
mended for locating the powerhouse:
The powerhouse should be safe from not only annual floods
but also rare flood events. Discussions should be held with
the local community members to ensure that floodwaters
have not reached the proposed powerhouse site within at
least the past 20 years. For micro-hydro schemes of 50-100
kW it is recommended that the powerhouse be above the
50-year flood level.
It should also be possible to discharge the tailwater safely
from the powerhouse back to the stream.
If possible the powerhouse should be located on level ground
to minimise excavation work.
The proposed location should be accessible throughout the
year. At some places this may require constructing a new
foot trail.
The powerhouse should be located close to the community
that it serves, provided that the penstock alignment and
other parameters are feasible and economical. This will
reduce the transmission line cost, and if agro-processing
units are also installed in the powerhouse, the community
will not have to carry their grain for a long distance.
Other stability issues discussed in Chapter 9 should also be
addressed.
8.3 Design of powerhouse
8.3.1 GENERAL
A powerhouse that is similar to other local houses in the
community is generally economical and appropriate. The
community members will be able to construct such a building
with nominal supervision.
If a decision is made to construct the powerhouse similar to
other local houses, then the civil design input required is to
size the plan area of the building and design the machine
Photo 8.3 Powerhouse of the Jhankre mini-hydro
foundation. The area inside the powerhouse should be well
lit and ventilated with sufficient windows. Placing a few
transparent fibreglass sheets (skylight) in the roof will provide
additional illumination as can be seen in Photograph 8.3.
8.3.2 SIZE OF THE POWERHOUSE
The plan area of the powerhouse should be determined as
follows:
The size of the electro-mechanical equipment should be
obtained from the manufacturer.
All required equipment should be drawn to scale and placed
on the proposed powerhouse plan area. This may require a
few trials to determine the optimum layout.
Adequate space should be provided such that all equipment
is easily accessible. There should be a clear spacing of at
least 1 m around each item of equipment that has moving
parts (such as the generator, turbine and the belt drive).
Noted that if agro-processing equipment is installed, the
community members will regularly visit the powerhouse
(to process their grain). Therefore additional space is
required so that the powerhouse does not become
overcrowded and a potential area for accidents. It is
recommended that such additional space is provided as a
lobby at the entrance and the equipment is placed beyond
it. A lobby large enough for five people to wait with their
grain (about 3m x 3m) may be adequate in most cases.
Adequate windows should be provided for lighting and
ventilation. Note that the door and windows need to be
located such that they do not obstruct access to the
equipment. This requires co-ordinating the locations of the
equipment, windows and the door.
The powerhouse layout of the Jhankre mini-hydro scheme is
shown in Figure 8.1.
8.3.3 POWERHOUSE WALL AND OTHER DETAILS
Most houses in the hills of Nepal are constructed of stone
masonry in mud mortar. Wooden truss with corrugated iron
sheet (CGI), slates or straw thatching are used for the roofs. A
similar building is recommended for the powerhouse structure
with the following considerations: